Daily Progress Report (DPR) in construction
The results of the planning and design process of a project are the Daily Progress Reports (DPRs). With the help of Livefield app, it is easy to make a DPR report.
The RFI procedure may seem simple, but it is frequently a cause of delays, costs, dispute, and, in some cases, litigation. As a result, it is in the best interest of all parties involved in construction projects to have a solid knowledge of how RFI function and how to utilize them effectively.
When it comes to the construction, RFIs are essential since they affect safety and quality while also affecting the project's budget, risk, and responsibility. Your approach to managing RFIs may make or break your project's timeliness and budget constraints.One million RFIs from 1,300 large construction projects across the globe were analyzed in 2013 by the Navigant Construction Forum. Median response time was 9.7 days, average cost to examine and reply to RFIs was $1,080, and average project had 796 RFIs.
When used effectively, RFIs aid in the construction of a structure that results in high-quality projects and satisfied customers. If you don't respond to RFIs in a timely manner, you may be liable for expensive reconstruction work and large costs to the at-fault party (i.e., the contractor, architect, or owner). Expenses are never welcomed by any of the parties involved.
RFI writing and response might be life or death. For example, the Hyatt Regency hotel in Kansas City, Missouri, collapsed in 1981 , killing 114 people. Failure to properly communicate design changes between architect and steel fabricator ultimately led to the construction's flaws, as discovered by an investigation.
There are many different kinds of RFI. A dozen or more different types are generally recognised by most companies. Here are the most widely acknowledged ones, along with a short description of what each includes and/or its purpose. Due to their similarities, some have been merged into one.
Sr. | Name | Purpose |
---|---|---|
1 | Change in Method or Process | When the contractor wants to change a specified building or installation technique. |
2 | Construction Coordination | Request to organize and coordinate construction-related procedures, schedules, and safety items. |
3 | Constructability Issues | When the construction document articulates a detail or design that the contractor deems infeasible. |
4 | Design Coordination | Organizing, communicating, and coordinating the design and associated documents among project participants. |
5 | Timing and Phasing | When the builder needs to change the sequence of construction activities due to resource or labour constraints. |
6 | Design Clarification | When the requester seeks more information about the design in order to better understand its details and how they relate to the project. |
7 | Design Change | To revise the design in order to facilitate construction or fix a construction mistake. |
8 | Deleted Scopes | To remove work from the project. |
9 | Incomplete Plans or Specs | This type of RFI points out errors or omissions in the plans and specifications. |
10 | Material Change | With this type of RFI, the requester seeks to use a different material than the construction documents specify. |
11 | Site Conditions | When builders discover a discrepancy between the description of site conditions in the construction documents and the actual site conditions. |
12 | Utility Conflict | When utility lines (such as water pipes or power wires) stand in the way of proceeding with construction as originally planned. |
13 | Value Engineering | To make changes for the purpose of reducing cost, improving efficiency, or enhancing quality. |
14 | Other Issues | Any other types of RFI that might come up, such as requests related to warranties, certifications and inspections, penalties, and non-design documents. |
Your RFI should be written in a manner that aids the architect, engineer, or other receiver in providing you with a timely response. Ensure that the format is standard, your query is properly stated, and that you provide relevant background, such as photographs.
Make sure your construction RFI includes the following elements:
The construction RFI process defines how inquiries are asked and answered over the course of a project. The RFI may be raised by a contractor or a subcontractor, and it may subsequently be sent to an architect or any other competent specialist for response.
The RFI may be resubmitted if the response is not satisfactory to the party that asked the question. Alternatively, the contractor may ask a meeting to discuss the matter further.
RFIs are often reviewed and mediated by a project manager on large-scale building projects. Because so many individuals are involved in these large projects, all parties handle RFIs electronically, preserving records of these paperwork and their responses. There should be a defined mechanism for allocating RFI tasks to each team member.
RFIs frustrate both issuer and responder. Following a few simple practises that will help ease or even eliminate this stress.
The Livefield platform makes it simple to plan, collect, manage, and report on work from any location, allowing your team to be more productive and do more work in less time. With real-time communication and automatic updates, you can make smarter, more informed choices while still completing your projects on schedule and under budget.
Livefield users commonly utilise the RFI features in most design and project management applications. They say that adopting Livefield to handle RFIs, along with other critical components of a construction project, makes the process smoother and simpler to follow.
Work productivity skyrockets when individuals and groups understand exactly what has to be done and why. Sign up now to get a free trial today.
We can help you to manage your project for better business revenue.
We can help you to manage your project for better business revenue.